Office of Conservation
Bayou Corne Field Update
Jan. 10, 2013 Activities
Texas Brine Operations
Oxy 3-A Cavern Well –
- Shut in, Vertical Seismic Profile being conducted through next 5 days
Texas Brine Facility Vent Well to Top of Aquifer (RW 1 on Oxy 2 well pad) –
- Flaring gas at 30.1 mcf/day
Texas Brine Facility Vent Well to Top of Cap Rock (RW 2 on Oxy 2 well pad) –
- Shut in pending plug and abandon
Texas Brine Facility Geophone Well (Between Oxy 2 & original Oxy 3 well pads) –
- Ongoing monitoring for seismic activity, data available at http://folkworm.ceri.memphis.edu/heli_temp/
Texas Brine Facility Shallow Pressure Monitoring (TBC 1-3)
TBC 1 (Original Oxy 3 well pad)
- Monitoring pressure
TBC 2 (Original Oxy 3 well pad)
- Monitoring pressure
TBC 3 (Oxy 1 well pad)
- Monitoring pressure
Sinkhole Site –
- Observing conditions
Conservation/Shaw Operations
ORW 1 Vent Well (North of Hwy 70)–
- Flaring gas at 10.73 mcf/day
ORW 2 Vent Well (North of Hwy 70)
- Flaring gas at 11.93 mcf/day
ORW 3 Vent Well (West of Bayou Corne) –
- Remains in monitoring status, set up to vent/flare natural gas if concentrations are observed around wellbore
ORW 4 Vent Well (South of Hwy 70) –
- Continuing work to clear perforations that have sanded in in order to restore natural gas flow for flaring
Bayou Corne Community
Bayou Corne Community Aquifer Monitoring Wells (BC 1-2)
BC 1
- Texas Brine reports awaiting landowner access to reach proposed site
BC 2
- Installed and completed, ongoing regular monitoring of pressure
Other Actions in Near-Term on Office of Conservation Directives
In status updates to Office of Conservation, Texas Brine reports:
- Order placed for indoor air monitoring equipment (LEL and H2S monitors and network components) for Bayou Corne community structures; based on signed owner agreements, initial monitors to be installed on Jan. 16
- Seeking land access for installation of ORW-6 vent well near Bayou Corne community south of Hwy. 70, pre-ordering well materials
- Installation of ORW-12 vent well (on Texas Brine facility near TBC 1 and 2) scheduled to begin once weather permits
- Received access approval to improve road and build site for Geophone 02 deep geotechnical well (proposed site near well access road east of sinkhole), and received permission to being constructing well site from state Office of Coastal Management and U.S. Army Corps of Engineers, mobilization to begin for site construction once weather permits
- Vibroseismic work currently scheduled for 3rd week of January, utilizing truck-mounted vibration generator in conjunction with surface seismic stations, Texas Brine facility geophone well and USGS monitoring stations
- Preparing joint coastal use application on sinkhole containment design for state Office of Coastal Management and U.S. Army Corps of Engineers