Containment Levee Project

 

On October 25, 2023, the Office of Conservation ordered (item 3.i) Westlake to create "a plan to construct a containment structure around the potential affected area at the surface." That plan can be found here.

Click here for the latest project timeline (updated 6/5/2025). 

Construction of the containment structure is ongoing and expected to be finished in late 2025. Daily updates are provided by Westlake to LDENR, and they can be found in the "Daily Reports" section of the menu above.

 

General plan of berm system with reference sections (Areas). Click here for full PDF.

 

 

Clearing across Area 1, October 22, 2024 - Click here for full-sized image.

 

Containment Levee Plans